A progress claim schedule is the spreadsheet a head contractor builds each month to claim from the principal: the value of work to date, what has already been claimed, variations, retention and GST. A commercial manager asks ChatGPT or Claude to check the arithmetic or tidy the layout, and the file goes with every subcontractor name, every package price and an internal notes column written for nobody else. This page marks every cell in a monthly claim schedule that rule 9 and privilege bear on, recomputes the totals, and shows how the same sheet is checked on Ermos inside the firm.

The head contractor’s progress claim schedule

Built each month by the head contractor, checked by the commercial manager and served on the principal with the supporting statement. Under section 13(1A) of the Building and Construction Industry Security of Payment Act 1999 (NSW), a payment claim may be served from the last day of the named month in which the work was first carried out and from the last day of each later month.

fx
ABCDEFGH
1ItemPackage (subcontractor)Value% doneValue to datePrevious claimsThis claimInternal note
21148,000.0060%88,800.0074,000.0014,800.00
32Strip-out (own forces)96,500.00100%96,500.0096,500.000.00
4370%130,480.0093,200.0037,280.00
5455%213,400.00155,200.0058,200.00
6545%118,800.0079,200.0039,600.00
76Joinery and finishes (not yet let)356,500.0010%35,650.000.0035,650.00
8718,350.00100%18,350.000.0018,350.00
9812,600.0050%6,300.000.006,300.00
10Total498,100.00
11Less retention at 5%
12GST at 10%
13Amount claimed this period, including GST
Claim 4Claim 3Subcontractors

An invented schedule. Every figure is recomputed: value to date is value times percentage done, this claim is value to date less previous claims, retention is 5% of this period’s gross claim and GST is 10% of the amount after retention. Hover or tap any highlighted item for the analysis; the full list is below.

Progress claim schedule builder

An Agent+ that builds the progress claim schedule from the head contract, the package values and the variation register. It works in your layout, carries retention and GST as the contract sets them, and marks any variation without a signed direction. The commercial manager gets a schedule ready to check.

What it does

  1. Reads the contract, package records and variation register
  2. Builds the schedule with retention and GST carried through
  3. Flags unsigned variations and internal notes for the manager

What stays with your people. The commercial manager checks every figure and note, and a partner decides what is served. The agent builds the schedule; it does not serve it.

An Agent+ is built once and anyone in the practice can run it. It works from your own documents and runs on Ermos Dominion, the AI unit in your office, or on Ermos Edge, your own instance in an Australian data centre.

What leaves the firm

  1. 1
    Subcontractor names against packages

    Who is engaged on the job and for what. A list of a head contractor’s subcontractors is confidential to the client under rule 9, and competing contractors and the subcontractors’ other customers would want it. Rule 9 confidentiality guide.

  2. 2
    The project and the end customer

    The building and the principal. Confidential to the client, and the principal is a third party whose fit-out is not public. Rule 9 confidentiality guide.

  3. 3
    The subcontract values

    The price of each package, from which the client’s whole cost position on the job can be read. Negotiated prices under confidentiality terms. Rule 9 confidentiality guide.

  4. 4
    The variations, one of them unsigned

    Two variations in the claim. The note says the principal’s representative has not signed one, which is a dispute in waiting and a fact the client would not volunteer. Legal privilege guide.

  5. 5
    The internal notes

    A hold-back against one subcontractor, a suspension threat from another, a partly estimated claim and an unsigned variation. Candid, internal and the lines the principal would most like to see. Legal privilege guide.

  6. 6
    The retention line

    The 5% held back from this claim. Retention is money held as security; section 12A of the Security of Payment Act lets regulations require a head contractor’s retention on a subcontract to be held in trust, and the regulations were not read. The rate is a contract term.

  7. 7
    The GST line

    A 10% line. The rate is public and the line names no one, though the tax treatment of retention is for the client’s tax adviser.

  8. 8
    The amount claimed and its formula

    The figure and how it is built. Under section 13(2) of the Act a payment claim must identify the work, indicate the claimed amount and state that it is made under the Act, and under section 13(7) a head contractor must not serve a claim on the principal without a supporting statement. A person checks every figure. Rule 9 confidentiality guide.

  9. 9
    The contract total and progress to date

    The total value of the job and how far it has progressed. The client’s overall position, which the principal and rivals would most like to benchmark. Rule 9 confidentiality guide.

  10. 10
    The preparer

    A named commercial manager. Ties the sheet to an individual and to the client’s processes. Supervising AI guide.

What happens in Frontier Models (ChatGPT, Claude)

  • The whole document is transmitted to the provider’s servers. On personal plans the user cannot choose where it is stored or processed, and for the major providers that has generally meant outside Australia, under that country’s legal process. Some business plans offer storage in Australia, but the provider still receives the content.
  • On consumer tiers, prompts can be retained and used to train future models.
  • The provider’s staff and systems can reach the content under the provider’s own policies.
  • Once sent, the firm no longer controls it. Retention and deletion happen on the provider’s terms.

The same document on Ermos

Ermos Dominion

The document is drafted on a unit in your office, from your own templates and the matter file. Every marked item stays on the unit, which keeps working with the internet switched off. Nothing in it is transmitted to an AI provider, so there is no disclosure to analyse: the confidentiality work is the same as for your file server.

Ermos Edge

Your documents, the index and your access boundaries stay on your own instance in an Australian data centre. When a staff member asks for this draft, only their question and the excerpts they are permitted to see go to a named Australian provider, who is contractually barred from keeping the content or training any model on it. Nothing is processed outside Australia.

Frontier Models (ChatGPT, Claude)Ermos EdgeErmos Dominion
Where the document is processedProvider servers, generally offshore on personal plansYour instance in an Australian data centre; answers generated in AustraliaThe unit in your office
Who can read itProvider staff and systems, under policyYour staff, within the boundaries you set. The named Australian provider processes only permitted excerpts, under contract, and keeps nothingYour staff only
Is it keptOn the provider’s termsKept on your instance; the provider is barred from retaining itStays on the unit
Can it train a modelOn consumer tiers, yesNo, by contractOnly your own unit learns from it, on your hardware

Part of Use cases in law firms.

Common questions

Do ChatGPT and Claude use the information in a progress claim spreadsheet?
Everything pasted or uploaded is sent to the AI company's servers and processed there to produce a reply. As at October 2026, whether a conversation on a personal plan (ChatGPT Free, Plus or Pro; Claude Free, Pro or Max) can be used to train the models depends on a setting each user controls. Business plans (ChatGPT Business and Enterprise, Claude Team and Enterprise) and the developer APIs sit under commercial terms, and OpenAI and Anthropic each say they do not train on that content by default (OpenAI, Anthropic). On either product, the thumbs up and thumbs down buttons can send a whole conversation back for training. This schedule carries Tolliver Plastering, Rushworth Electrical and Yeoman Air Conditioning against their package prices, and a notes column about a suspension threat and a variation the principal has not signed.
Is it safe to paste a progress claim spreadsheet into ChatGPT or Claude?
No, because the sheet shows the client's whole cost position on the job, from the total of $1,470,350 to the amount claimed of $219,638.10, and its notes column is privileged. The Office of the Australian Information Commissioner (OAIC) recommends in its guidance on commercially available AI products that organisations do not enter personal information, and particularly sensitive information, into publicly available generative AI tools, because of the significant and complex privacy risks. It also names Winifred Sato, the principal's representative, and R. Thakur, the commercial manager, who are individuals as well as contacts.
What travels with a progress claim spreadsheet when it is uploaded to ChatGPT or Claude?
An uploaded file leaves the business as a whole file, which can carry other sheets, hidden columns, comments, tracked changes and file properties. This workbook has tabs named Claim 3 and Subcontractors beside Claim 4, and an upload could carry all of them with the internal notes column and the formula that builds the amount claimed. The OAIC's guidance also tells organisations to review carefully the terms and settings that will apply to their use of any AI product.
How can a law firm use AI for a progress claim spreadsheet without sending it to ChatGPT or Claude?
Ermos is built so the document stays under your control. On the Dominion AI unit it is drafted inside your office and none of it is sent to an AI provider. On Ermos Edge your documents and index stay on your own instance in an Australian data centre, and only the question and the excerpts the user is permitted to see go to a named Australian provider that is contractually barred from keeping them or training any model on them. The schedule is checked against the subcontracts, the previous claims and the firm's own payment claim checklist. A solicitor recomputes every figure and checks the claim against section 13 of the Security of Payment Act before it is served.
What must a payment claim under the NSW Security of Payment Act contain?
As that Act read in a January 2026 version, section 13(2) requires a payment claim to identify the construction work or related goods and services it relates to, indicate the amount claimed and state that it is made under the Act. A head contractor serving a claim on the principal must also attach a supporting statement in the form approved by the Secretary, under section 13(7).
How often can a payment claim be served?
Section 13(1A) allows a payment claim to be served from the last day of the named month in which work was first carried out, and from the last day of each later month, and section 13(1B) lets the contract set an earlier date. Section 13(5) generally allows one claim for work in a named month, and section 13(6) lets a claim include an amount from a previous claim.
What does retention mean in a construction contract?
Retention is money held back from progress payments as security for the other side's performance, often a percentage of each payment. Section 12A of the Security of Payment Act defines retention money as money a head contractor retains from money payable to a subcontractor as security for the subcontractor's obligations, and lets regulations require it to be held in trust.