Law Firm Progress Claim Schedules: Use case and AI Confidentiality
A progress claim schedule is the spreadsheet a head contractor builds each month to claim from the principal: the value of work to date, what has already been claimed, variations, retention and GST. A commercial manager asks ChatGPT or Claude to check the arithmetic or tidy the layout, and the file goes with every subcontractor name, every package price and an internal notes column written for nobody else. This page marks every cell in a monthly claim schedule that rule 9 and privilege bear on, recomputes the totals, and shows how the same sheet is checked on Ermos inside the firm.
The head contractor’s progress claim schedule
Built each month by the head contractor, checked by the commercial manager and served on the principal with the supporting statement. Under section 13(1A) of the Building and Construction Industry Security of Payment Act 1999 (NSW), a payment claim may be served from the last day of the named month in which the work was first carried out and from the last day of each later month.
| A | B | C | D | E | F | G | H | |
|---|---|---|---|---|---|---|---|---|
| 1 | Item | Package (subcontractor) | Value | % done | Value to date | Previous claims | This claim | Internal note |
| 2 | 1 | Preliminaries and site establishment, Level 3, 19 Marsh Street, for Roundel Advisory2 | 148,000.00 | 60% | 88,800.00 | 74,000.00 | 14,800.00 | |
| 3 | 2 | Strip-out (own forces) | 96,500.00 | 100% | 96,500.00 | 96,500.00 | 0.00 | |
| 4 | 3 | Partitions and ceilings (Tolliver Plastering)1 | 186,400.003 | 70% | 130,480.00 | 93,200.00 | 37,280.00 | Hold $6,000 until Tolliver closes its WHS audit items5 |
| 5 | 4 | Electrical (Rushworth Electrical)1 | 388,000.003 | 55% | 213,400.00 | 155,200.00 | 58,200.00 | Rushworth has threatened to suspend work if claim 3 is not paid5 |
| 6 | 5 | Mechanical and fire (Yeoman Air Conditioning)1 | 264,000.003 | 45% | 118,800.00 | 79,200.00 | 39,600.00 | |
| 7 | 6 | Joinery and finishes (not yet let) | 356,500.00 | 10% | 35,650.00 | 0.00 | 35,650.00 | Part of this is a timing estimate; check before the claim goes out5 |
| 8 | 7 | Variation 1: relocate server room wall (directed 14 October)4 | 18,350.00 | 100% | 18,350.00 | 0.00 | 18,350.00 | |
| 9 | 8 | Variation 2: acoustic lining to boardroom4 | 12,600.00 | 50% | 6,300.00 | 0.00 | 6,300.00 | The principal’s representative, Winifred Sato, has not signed the direction; claim anyway5 |
| 10 | Total | 1,470,350.009 | 708,280.009 | 498,100.00 | 210,180.008 | |||
| 11 | Less retention at 5% | (10,509.00)6 | ||||||
| 12 | GST at 10% | 19,967.107 | ||||||
| 13 | Amount claimed this period, including GST | 219,638.108 | Prepared by R. Thakur, commercial manager10 |
An invented schedule. Every figure is recomputed: value to date is value times percentage done, this claim is value to date less previous claims, retention is 5% of this period’s gross claim and GST is 10% of the amount after retention. Hover or tap any highlighted item for the analysis; the full list is below.
Progress claim schedule builder
An Agent+ that builds the progress claim schedule from the head contract, the package values and the variation register. It works in your layout, carries retention and GST as the contract sets them, and marks any variation without a signed direction. The commercial manager gets a schedule ready to check.
What it does
- Reads the contract, package records and variation register
- Builds the schedule with retention and GST carried through
- Flags unsigned variations and internal notes for the manager
What stays with your people. The commercial manager checks every figure and note, and a partner decides what is served. The agent builds the schedule; it does not serve it.
An Agent+ is built once and anyone in the practice can run it. It works from your own documents and runs on Ermos Dominion, the AI unit in your office, or on Ermos Edge, your own instance in an Australian data centre.
What leaves the firm
- 1Subcontractor names against packages
Who is engaged on the job and for what. A list of a head contractor’s subcontractors is confidential to the client under rule 9, and competing contractors and the subcontractors’ other customers would want it. Rule 9 confidentiality guide.
Frontier Models (ChatGPT, Claude) Transmitted to the provider, generally offshore on personal plans Ermos Edge Stays on your instance in Australia; leaves only inside a permitted excerpt, per question, to the named provider Ermos Dominion Stays on the unit in your office Use case Progress claim schedule builder. Builds the monthly claim schedule from the contract, package records and variation register, and flags unsigned variations and notes that should not travel with the claim. See the use case - 2The project and the end customer
The building and the principal. Confidential to the client, and the principal is a third party whose fit-out is not public. Rule 9 confidentiality guide.
Frontier Models (ChatGPT, Claude) The project and the principal transmitted Ermos Edge Stays on your instance in Australia; leaves only inside a permitted excerpt, per question, to the named provider Ermos Dominion Stays on the unit in your office Use case Progress claim schedule builder. Builds the monthly claim schedule from the contract, package records and variation register, and flags unsigned variations and notes that should not travel with the claim. See the use case - 3The subcontract values
The price of each package, from which the client’s whole cost position on the job can be read. Negotiated prices under confidentiality terms. Rule 9 confidentiality guide.
Frontier Models (ChatGPT, Claude) Every package price transmitted Ermos Edge Stays on your instance in Australia; leaves only inside a permitted excerpt, per question, to the named provider Ermos Dominion Stays on the unit in your office Use case Progress claim schedule builder. Builds the monthly claim schedule from the contract, package records and variation register, and flags unsigned variations and notes that should not travel with the claim. See the use case - 4The variations, one of them unsigned
Two variations in the claim. The note says the principal’s representative has not signed one, which is a dispute in waiting and a fact the client would not volunteer. Legal privilege guide.
Frontier Models (ChatGPT, Claude) A variation the principal has not signed transmitted Ermos Edge Stays on your instance in Australia; leaves only inside a permitted excerpt, per question, to the named provider Ermos Dominion Stays on the unit in your office Use case Progress claim schedule builder. Builds the monthly claim schedule from the contract, package records and variation register, and flags unsigned variations and notes that should not travel with the claim. See the use case - 5The internal notes
A hold-back against one subcontractor, a suspension threat from another, a partly estimated claim and an unsigned variation. Candid, internal and the lines the principal would most like to see. Legal privilege guide.
Frontier Models (ChatGPT, Claude) Candid internal notes now on a third party’s servers; on consumer tiers it can train future models Ermos Edge Stays on your instance in Australia; leaves only inside a permitted excerpt, per question, to the named provider Ermos Dominion Stays on the unit in your office Use case Progress claim schedule builder. Builds the monthly claim schedule from the contract, package records and variation register, and flags unsigned variations and notes that should not travel with the claim. See the use case - 6The retention line
The 5% held back from this claim. Retention is money held as security; section 12A of the Security of Payment Act lets regulations require a head contractor’s retention on a subcontract to be held in trust, and the regulations were not read. The rate is a contract term.
Frontier Models (ChatGPT, Claude) A rate and a retention figure; low value alone Ermos Edge The AI can mis-add; a person must recompute the retention Ermos Dominion Stays on the unit, but the AI can mis-add; a person must recompute Use case Progress claim schedule builder. Builds the monthly claim schedule from the contract, package records and variation register, and flags unsigned variations and notes that should not travel with the claim. See the use case - 7The GST line
A 10% line. The rate is public and the line names no one, though the tax treatment of retention is for the client’s tax adviser.
Frontier Models (ChatGPT, Claude) A public rate, but the sum lets the net claim be worked back; low value alone Ermos Edge A calculation a person must check Ermos Dominion A calculation a person must check Use case Progress claim schedule builder. Builds the monthly claim schedule from the contract, package records and variation register, and flags unsigned variations and notes that should not travel with the claim. See the use case - 8The amount claimed and its formula
The figure and how it is built. Under section 13(2) of the Act a payment claim must identify the work, indicate the claimed amount and state that it is made under the Act, and under section 13(7) a head contractor must not serve a claim on the principal without a supporting statement. A person checks every figure. Rule 9 confidentiality guide.
Frontier Models (ChatGPT, Claude) The amount claimed and how it is built transmitted Ermos Edge The AI can mis-add; a solicitor must recompute every figure and check the sections Ermos Dominion Stays on the unit, but the AI can mis-add; a solicitor must recompute every figure Use case Progress claim schedule builder. Builds the monthly claim schedule from the contract, package records and variation register, and flags unsigned variations and notes that should not travel with the claim. See the use case - 9The contract total and progress to date
The total value of the job and how far it has progressed. The client’s overall position, which the principal and rivals would most like to benchmark. Rule 9 confidentiality guide.
Frontier Models (ChatGPT, Claude) The whole job’s value and progress transmitted Ermos Edge Stays on your instance in Australia; leaves only inside a permitted excerpt, per question, to the named provider Ermos Dominion Stays on the unit in your office Use case Progress claim schedule builder. Builds the monthly claim schedule from the contract, package records and variation register, and flags unsigned variations and notes that should not travel with the claim. See the use case - 10The preparer
A named commercial manager. Ties the sheet to an individual and to the client’s processes. Supervising AI guide.
Frontier Models (ChatGPT, Claude) Transmitted, and the leak is traceable to you Ermos Edge Stays on your instance in Australia; leaves only inside a permitted excerpt, per question, to the named provider Ermos Dominion Stays on the unit in your office Use case Progress claim schedule builder. Builds the monthly claim schedule from the contract, package records and variation register, and flags unsigned variations and notes that should not travel with the claim. See the use case
What happens in Frontier Models (ChatGPT, Claude)
- The whole document is transmitted to the provider’s servers. On personal plans the user cannot choose where it is stored or processed, and for the major providers that has generally meant outside Australia, under that country’s legal process. Some business plans offer storage in Australia, but the provider still receives the content.
- On consumer tiers, prompts can be retained and used to train future models.
- The provider’s staff and systems can reach the content under the provider’s own policies.
- Once sent, the firm no longer controls it. Retention and deletion happen on the provider’s terms.
The same document on Ermos
Ermos Dominion
The document is drafted on a unit in your office, from your own templates and the matter file. Every marked item stays on the unit, which keeps working with the internet switched off. Nothing in it is transmitted to an AI provider, so there is no disclosure to analyse: the confidentiality work is the same as for your file server.
Ermos Edge
Your documents, the index and your access boundaries stay on your own instance in an Australian data centre. When a staff member asks for this draft, only their question and the excerpts they are permitted to see go to a named Australian provider, who is contractually barred from keeping the content or training any model on it. Nothing is processed outside Australia.
| Frontier Models (ChatGPT, Claude) | Ermos Edge | Ermos Dominion | |
|---|---|---|---|
| Where the document is processed | Provider servers, generally offshore on personal plans | Your instance in an Australian data centre; answers generated in Australia | The unit in your office |
| Who can read it | Provider staff and systems, under policy | Your staff, within the boundaries you set. The named Australian provider processes only permitted excerpts, under contract, and keeps nothing | Your staff only |
| Is it kept | On the provider’s terms | Kept on your instance; the provider is barred from retaining it | Stays on the unit |
| Can it train a model | On consumer tiers, yes | No, by contract | Only your own unit learns from it, on your hardware |
Part of Use cases in law firms.
Common questions
Do ChatGPT and Claude use the information in a progress claim spreadsheet?
Is it safe to paste a progress claim spreadsheet into ChatGPT or Claude?
What travels with a progress claim spreadsheet when it is uploaded to ChatGPT or Claude?
How can a law firm use AI for a progress claim spreadsheet without sending it to ChatGPT or Claude?
What must a payment claim under the NSW Security of Payment Act contain?
How often can a payment claim be served?
What does retention mean in a construction contract?
See Dominion answering from your own documents.
A demonstration takes 30 minutes, uses no client data, and comes with no obligation.
Book a demo